Jawa 7 Power Plant, Indonesia

Project Profile

Name    :Jawa 7 Power Plant
Location : Jawa, Indonesia
Method  : VCM

Construction duration
From : 2016.05
To     : 2017.07

Jawa 7 Power Plant is one of the largest coal fired power plant with 2*1000 MW capacity in Indonesia. The project is located at low land area with a lot of fish pool and swampy area. Vacuum Consolidation method is used to improve the soft clay to help the overall construction period to fulfill the very tight period requirement.

301.jpg302.jpg303.jpg