PIK Golf Island,Jakarta

Project Profile
Name    :PIK Golf Island
Location : Jakarta, Indonesia
Method  : Dynamic Compaction, Vibroflotation

Construction duration
From : 2014.02
To     : 2017.08

PIK Golf Island is the first huge scale reclamation artificial island in Indonesia. The total area was formed is more than 313 hectares. Dynamic compaction and Vibroflotation method are used to compact the loose sand of the whole island.