Our services include ground improvement, piling, deep excavation and marine construction works . For the ground improvement works, with patent technology HVDM and other traditional techniques, we are able to treat soil and sand at different conditions.

Engineering case

Shanghai Pudong International Airport, China

Project Profile
Name     : Pudong International Airport
Location : Shanghai, China
Method   : HVDM

Construction duration
From : 2003.06
To     : 2005.10

Pudong International Airport, a competition was run among 7 schemes for treating soft ground (1,110, 000 m2) of the 2nd runway of Shanghai Pudong Int’l Airport. HVDM won by its high quality, low cost, and fast construction. Shanghai Airport website posted the project event, saying “No.1 Nationwide” and “well above the design standard", and “saving over RMB 100 million". The 3rd runway would continue to use the method.