Wuhan Huangpi xinwu lake pipe jacking of water extraction project and jet grouting pile construction.

Project Profile
Name      Wuhan Huangpi xinwu lake pipe jacking of water extraction project and jet grouting pile construction.

Location  : Wuhan city

Method    : Pipe Jacking and jet grouting pile

Construction duration
From : 2013.04
To     : 2014.02

Project introduction: This project is mainly divided into two parts, pipe jacking construction and jet grouting pile strengthening engineering. Two different pipe diameter and pipe material is used in the project, DN1500 steel pipe and DN2700 reinforced concrete pipe are jacked through the lifting jack and the caisson method is adopted to construct working wells. The construction of double-barrelled high-pressure jet grouting pile is also included in this project and the diameter of the pile is 600mm.